week 26

In week 26 the fences around the site were removed and Dijkhof completed the final work on the paving.
We have started placing the ornaments in the garden and Hovenier Langenhuizen will shortly start planting.

The profiles are also being finished on the glazing of the meeting room on the outside of the building.

Everyone, including the painters, is working really hard to make the work is completed on schedule.

Gedo is finishing the E-installation, while Prinssen is completing and making adjustments to the W-installation.

The furniture, supplied by Havic, Veghel, has already been delivered and is currently being assembled and placed in position.

Our own engineers are busy in the industrial hall installing the pipes for compressed air and gas welding and equipping the work stations.

The final inspection before completion will be done shortly by builders Van de Ven, project managers Miba and IVS Dosing Technology.

Our move to Doornhoek 3810, Veghel is planned for  14 and 15 July.